Short answer: most of our custom pools take 16 to 28 weeks from the first design meeting to the first swim. An oceanfront lot that needs the state's coastal permit adds months on top, because that review runs on its own clock.
Where the time goes
| Stage | Typical time | What sets the pace |
|---|---|---|
| Find the fit | 1 to 2 weeks | How fast we get your survey and find a site visit date |
| Design | 2 to 6 weeks | Pool Design presents in about 2 weeks, Estate designs in about 4, plus your revision rounds |
| Engineering and local permit | 2 to 6 weeks | The office reviewing it and how complete the package is |
| State coastal permit (oceanfront only) | Months | The state's review, and whether anything changes after submission |
| Construction | 10 weeks to several months | Size, raised walls, water features, weather and inspections |
Why oceanfront takes longer
Anything seaward of the Coastal Construction Control Line needs a Florida Department of Environmental Protection permit as well as the local one. That review only starts once the design is complete, and a change after submission restarts it. On our 2026 Ponce Inlet project, a pool on 15 to 20 foot pilings, it took about eleven months from contract to the state permit. Construction on pilings and raised walls also takes longer than a pool set in the ground.
The way to protect your date is to finish design early and freeze it. We start the state review as soon as the design allows, and we do not touch the submitted plans unless you ask us to.
What happens in construction
Layout and excavation
We stake the pool, walk it with you, then dig.
Steel and plumbing
Steel to the engineered schedule, plumbing set and pressure-tested, then inspected.
Gunite shell
Sprayed, shaped and left to cure. Curing is time you cannot rush.
Tile, coping and deck
Often the longest stretch on a luxury pool, because this is where the stonework is.
Interior finish and start-up
The finish goes on, the pool is filled and balanced, and we teach you how to run it.
What you can do to keep it moving
- Send your survey and HOA guidelines at the start.
- Settle your target investment on the first call, so design does not need a second pass.
- Make finish selections during design, not during construction.
- Decide on the fence or screen enclosure in design. The barrier is part of the permit.
- If you are building a house, bring us in when the site plan is drawn.
We build about 26 to 30 custom pools a year, so each one has a dedicated project manager who sends you an update every week.